The marketing team is transitioning to using hybrid approaches for their projects. The marketing director is not knowledgeable about hybrid methodologies, and the project manager needs the director's support as the marketing director is a key stakeholder.

What should the project manager do to obtain the support?

A.
Train the marketing team and keep the director informed.
Answers
A.
Train the marketing team and keep the director informed.
B.
Mentor the marketing director on hybrid approaches.
Answers
B.
Mentor the marketing director on hybrid approaches.
C.
Ask the marketing team members to coach the director.
Answers
C.
Ask the marketing team members to coach the director.
D.
Ask the marketing director to participate in daily meetings.
Answers
D.
Ask the marketing director to participate in daily meetings.
Suggested answer: B