Question 820 - PMP discussion
A project manager notices that a project participant seems frustrated and expresses themselves loudly at status meetings and later discovers that the participant is hearing impaired. Which process should the project manager have used at the start of the protect that would have identified this situation?
A.
Stakeholder analysis
B.
Resource needs analysis
C.
Accommodations assessment
D.
Team member assessment