A project manager notices that a project participant seems frustrated and expresses themselves loudly at status meetings and later discovers that the participant is hearing impaired. Which process should the project manager have used at the start of the protect that would have identified this situation?

A.
Stakeholder analysis
Answers
A.
Stakeholder analysis
B.
Resource needs analysis
Answers
B.
Resource needs analysis
C.
Accommodations assessment
Answers
C.
Accommodations assessment
D.
Team member assessment
Answers
D.
Team member assessment
Suggested answer: A