List of questions
Related questions
Question 823 - PMP discussion
A project manager is using a hybrid approach to comply with a regulatory requirement. The planning and closing phases will use a predictive approach, and the execution phase will use an iterative approach. During the second sprint review, the project sponsor requested a change in priority tor some of the product backlog items.
What should the project manager do as a servant leader?
A.
Ask the sponsor to submit a change request to the change control board (CCB)
B.
Support the product owners decision to change the priority of the product backlog items
C.
Accept the request and include the product backlog items in the next sprint
D.
Review the impact of the change on the schedule management plan baseline
Your answer:
0 comments
Sorted by
Leave a comment first