A project sponsor wants to develop software that would have 30 features and would be used in 10 different countries. The team feels overwhelmed with the amount of work to be done. What should the project manager do?

A.
Encourage and motivate the team with project incentives
Answers
A.
Encourage and motivate the team with project incentives
B.
Subdivide the team to handle different aspects of the project
Answers
B.
Subdivide the team to handle different aspects of the project
C.
Support the team to find and execute the minimum viable product (MVP)
Answers
C.
Support the team to find and execute the minimum viable product (MVP)
D.
Organize project execution to satisfy the project sponsor s request
Answers
D.
Organize project execution to satisfy the project sponsor s request
Suggested answer: C