Question 826 - PMP discussion
A project manager primarily works on implementation projects Depending on the deliverable, the project manager is able to estimate the time line based on previous projects. The project manager now receives a project that is different from the previous implementation projects.
What should the project manager do next?
A.
Refer to the previous protect they worked on and base the estimate on that
B.
Use expert judgment to estimate the schedule and then adjust the schedule as the project progresses
C.
Ask the project management office (PMO) by when the project can be completed and use that date as the project time line
D.
Break down the project into smaller tasks and estimate the durations of the activities
Your answer:
0 comments
Sorted by
Leave a comment first