List of questions
Related questions
Question 846 - PMP discussion
A new project manager is working on a time-sensitive social media strategy for a software development company that is building a communications management plan for the stakeholders.
This is the first major project since the company shifted to working remotely on a full-time basis.
After reviewing all previous company artifacts, the project manager finds a standard operating procedure (SOP) document outlining how all communication should take place.
How should the project manager proceed?
A.
Adhere to the SOP for the project, make a note of required changes, and escalate to the change management board.
B.
Use the SOP as a base plan and make updates during the control and monitoring phase of the project.
C.
Ignore the SOP and write a separate communications management plan for this project.
D.
Assess the SOP for relevancy, make updates, and circulate to the stakeholders for comment during project planning.
Your answer:
0 comments
Sorted by
Leave a comment first