A project is being executed in multiple phases. Midway through, the customer wants to bring in a new tool to replace the existing software in the project as part of their improvement program. The project team has identified the changes and submitted the change request to the customer for approval What should the project manager do next?
A.
Prioritize the impact of the change and modify the project management plan.
B.
Inform management of the customer's organizational change.
C.
Examine the business value of the change request.
D.
Perform a team-skills versus project-skills analysis.