List of questions
Related questions
Question 854 - PMP discussion
A project sponsor asked the product owner to deliver the functionality that provides the highest return on investment (ROI) as soon as possible. Which artifact should the project lead use to track benefits?
A.
Requirements backlog
B.
Product backlog
C.
Project charter
D.
Project scope
Your answer:
0 comments
Sorted by
Leave a comment first