List of questions
Related questions
Question 855 - PMP discussion
A project has progressed significantly and is getting close to completion. The project manager observed that team members are no longer focused and have started arriving to work late.
What should the project manager do?
A.
Engage functional managers to secure roles for team members.
B.
Hold motivation sessions to keep team member morale high.
C.
Ask for replacement project team members.
D.
Penalize team members who arrive to work late.
Your answer:
0 comments
Sorted by
Leave a comment first