Question 856 - PMP discussion
A project manager is leading a project to develop a new mobile application. During an informal conversation, a stakeholder asked the project manager to add new features to the current sprint.
What should the project manager do?
A.
Request the stakeholder to wait until the following sprint planning.
B.
Discuss this demand during the following standup meeting.
C.
Accept the change request and negotiate the time line.
D.
Ask the product owner to discuss this request with the stakeholder.
Your answer: