Question 858 - PMP discussion
During the initiation phase, a sponsor recommends that all team members should be colocated. Some of the team members need a significant amount of time to commute, and there is no office space available.
What should the project manager do?
A.
Log this as a risk, since colocating the team will require additional costs.
B.
Colocate the project team because that is what the sponsor requested.
C.
Assess the business benefits of a colocated project team.
D.
Colocate the project team because it will increase efficiency.