During the initiation phase, a sponsor recommends that all team members should be colocated. Some of the team members need a significant amount of time to commute, and there is no office space available.

What should the project manager do?

A.
Log this as a risk, since colocating the team will require additional costs.
Answers
A.
Log this as a risk, since colocating the team will require additional costs.
B.
Colocate the project team because that is what the sponsor requested.
Answers
B.
Colocate the project team because that is what the sponsor requested.
C.
Assess the business benefits of a colocated project team.
Answers
C.
Assess the business benefits of a colocated project team.
D.
Colocate the project team because it will increase efficiency.
Answers
D.
Colocate the project team because it will increase efficiency.
Suggested answer: C