Question 859 - PMP discussion
An organizational policy requires project managers to carry out two audits per month: one for their own project and one for another project manager's project. After a recent audit review, team members suggested that it is not fair to have their deliverables audited by a peer.
What should the project manager do to avoid this situation?
A.
Ask the organization to remind staff that audits are a requirement.
B.
Use casual meetings instead of audits.
C.
Complete the audits less frequently.
D.
Set up an audit policy in the scope management plan.
Your answer: