An organizational policy requires project managers to carry out two audits per month: one for their own project and one for another project manager's project. After a recent audit review, team members suggested that it is not fair to have their deliverables audited by a peer.

What should the project manager do to avoid this situation?

A.
Ask the organization to remind staff that audits are a requirement.
Answers
A.
Ask the organization to remind staff that audits are a requirement.
B.
Use casual meetings instead of audits.
Answers
B.
Use casual meetings instead of audits.
C.
Complete the audits less frequently.
Answers
C.
Complete the audits less frequently.
D.
Set up an audit policy in the scope management plan.
Answers
D.
Set up an audit policy in the scope management plan.
Suggested answer: D