ExamGecko
Home Home / PMI / PMP
Question list
Search
Search

List of questions

Search

Related questions











Question 861 - PMP discussion

Report
Export

A new quality report was distributed to stakeholders after the sponsor approved it. A senior manager requests changing the colors and sizes of some of the graphs included in the report.

What should the project manager do?

A.
Reject the change as the report was approved previously.
Answers
A.
Reject the change as the report was approved previously.
B.
Incorporate the change in a future report.
Answers
B.
Incorporate the change in a future report.
C.
Ask the team to make the manager's requested changes.
Answers
C.
Ask the team to make the manager's requested changes.
D.
Advise the manager to raise a change request.
Answers
D.
Advise the manager to raise a change request.
Suggested answer: D
asked 23/09/2024
Hector Quintero
47 questions
User
Your answer:
0 comments
Sorted by

Leave a comment first