Question 861 - PMP discussion
A new quality report was distributed to stakeholders after the sponsor approved it. A senior manager requests changing the colors and sizes of some of the graphs included in the report.
What should the project manager do?
A.
Reject the change as the report was approved previously.
B.
Incorporate the change in a future report.
C.
Ask the team to make the manager's requested changes.
D.
Advise the manager to raise a change request.
Your answer: