List of questions
Related questions
Question 862 - PMP discussion
During a planning session, the development team and the product owner are arguing about the effort needed to deliver a specific feature in a software development project. The product owner says that the feature can be developed in one week, whereas the team estimates that it will take at least two weeks. After several hours of discussion, they have not reached an agreement.
What should the project lead do?
A.
Decide what should be the time estimate and proceed with the planning meeting.
B.
Educate the product owner that the project team members are the most appropriate group for assessing the effort.
C.
Ask the project team to accept the shorter estimate as it is important to keep a good relationship with the product owner.
D.
Communicate to the stakeholders that the project has to be delayed for two weeks.
Your answer:
0 comments
Sorted by
Leave a comment first