Question 863 - PMP discussion
There are two interdependent projects: the first project is in execution, and the second one is about to be deployed. The first project has been delayed, which is now affecting the second project due to the sharing of resources.
What should the project manager do in this situation?
A.
Ask for written commitment from the team manager assuring the deployment team can work on only one of the projects.
B.
Assess the issue with the deployment resources' availability and define a plan to deploy extra resources to the deployment team.
C.
Organize a meeting with the deployment team and explain that, due to a resource shortage, the project will be delayed.
D.
Ask the procurement team to solicit offers from external providers in order to replace the internal resources for the deployment.