ExamGecko
Home Home / PMI / PMP
Question list
Search
Search

List of questions

Search

Related questions











Question 866 - PMP discussion

Report
Export

A customer asks the project manager to complete a project 10 days earlier than planned due to marketing constraints. After discussing this request with the project team, the project manager concludes that this can be achieved if a few activities can be overlapped.

Which approach should the project manager take?

A.
Fast-track the activities based on limitations and dependencies.
Answers
A.
Fast-track the activities based on limitations and dependencies.
B.
Release the minimum viable product (MVP) earlier and enhance it in the next iteration.
Answers
B.
Release the minimum viable product (MVP) earlier and enhance it in the next iteration.
C.
Review the schedule and perform resource leveling.
Answers
C.
Review the schedule and perform resource leveling.
D.
Add subject matter experts (SMEs) to perform the project activities in parallel.
Answers
D.
Add subject matter experts (SMEs) to perform the project activities in parallel.
Suggested answer: A
asked 23/09/2024
aakriti grover
51 questions
User
Your answer:
0 comments
Sorted by

Leave a comment first