Question 866 - PMP discussion
A customer asks the project manager to complete a project 10 days earlier than planned due to marketing constraints. After discussing this request with the project team, the project manager concludes that this can be achieved if a few activities can be overlapped.
Which approach should the project manager take?
A.
Fast-track the activities based on limitations and dependencies.
B.
Release the minimum viable product (MVP) earlier and enhance it in the next iteration.
C.
Review the schedule and perform resource leveling.
D.
Add subject matter experts (SMEs) to perform the project activities in parallel.