A team is about to close a deployment and is waiting to receive critical information from the customer. The customer continues to postpone sending information, which is consequently delaying the deployment.

What should the project manager have done to prevent the delay?

A.
Delegated the task to the product owner
Answers
A.
Delegated the task to the product owner
B.
Asked the team to use the sample data
Answers
B.
Asked the team to use the sample data
C.
Engaged the sponsor and sought their support
Answers
C.
Engaged the sponsor and sought their support
D.
Received all key information ahead of time
Answers
D.
Received all key information ahead of time
Suggested answer: D