A project defined to be executed in four months is divided into eight iterations. During its first retrospective, the team realizes that only one member has experience doing a key project requirement.

What should the project manager do?

A.
Invite the team member to share experience in the next retrospective.
Answers
A.
Invite the team member to share experience in the next retrospective.
B.
Ask the sponsor to add team members with the required experience.
Answers
B.
Ask the sponsor to add team members with the required experience.
C.
Plan knowledge-sharing sessions within the team.
Answers
C.
Plan knowledge-sharing sessions within the team.
D.
Ask the sponsor for a training course for the team.
Answers
D.
Ask the sponsor for a training course for the team.
Suggested answer: C