A company's project management office (PMO) is incorporating more adaptive technologies and has hired a new project manager with hybrid project management experience. The team is slow in adopting the new methodology and has not been updating project artifacts in a timely manner.
Which action should the project manager take to improve the team's performance?
A.
Send an email asking all project team members to complete updates at the end of the day.
B.
Speak individually with each project team member about making the needed updates.
C.
Set up a training session for all project team members.
D.
Reach out to the functional managers for support.