A company is launching a new product and decides to transition from a predictive to an agile approach. During the third sprint, the project manager notices that the team is not working as a cohesive unit.

Which two rules are appropriate for the project manager to instill in the team? (Choose two.)

A.
Work together daily as a team.
Answers
A.
Work together daily as a team.
B.
Strive toward continuous improvement.
Answers
B.
Strive toward continuous improvement.
C.
Send communications to the entire team.
Answers
C.
Send communications to the entire team.
D.
Follow the sprint planning.
Answers
D.
Follow the sprint planning.
E.
Only share suggestions at the end of the sprint.
Answers
E.
Only share suggestions at the end of the sprint.
Suggested answer: A, B