Question 880 - PMP discussion

Report
Export

A project manager is working on a large project with a very difficult client. During the course of the project, the project manager realizes that if the project team had a little more time and funding to make some minor changes, the client could realize the benefits of 25% of the project outcomes early.

How should the project manager approach this?

A.
Concentrate on the current project milestones.
Answers
A.
Concentrate on the current project milestones.
B.
Make all the changes and then show the client the results.
Answers
B.
Make all the changes and then show the client the results.
C.
Develop a business case and submit it to the client.
Answers
C.
Develop a business case and submit it to the client.
D.
Update the project management plan for this new work.
Answers
D.
Update the project management plan for this new work.
Suggested answer: C