A project manager identified a risk on a deliverable completed by a contractor and added it to the risk register. During the last inspection meeting for the deliverable, the project manager notices that the suggested mitigation did not produce the expected results.

How should the project manager proceed?

A.
Review the procurement performance to identify the root cause
Answers
A.
Review the procurement performance to identify the root cause
B.
Reevaluate the probability of the risk occurrence and mitigation strategy.
Answers
B.
Reevaluate the probability of the risk occurrence and mitigation strategy.
C.
Issue a change request to apply the risk response plan for this risk.
Answers
C.
Issue a change request to apply the risk response plan for this risk.
D.
Audit the procurement process to identify why the mitigation did not work.
Answers
D.
Audit the procurement process to identify why the mitigation did not work.
Suggested answer: B