A project manager is assigned to a project. The project schedule and costs are tight, and the project manager determined that there is a lack of resources to deliver this project.

What should the project manager do?

A.
Identify the resource requirements and communicate them to the stakeholders seeking resources.
Answers
A.
Identify the resource requirements and communicate them to the stakeholders seeking resources.
B.
Update the risk register noting that, due to the lack of available resources, the project is likely to be delayed.
Answers
B.
Update the risk register noting that, due to the lack of available resources, the project is likely to be delayed.
C.
Define the work breakdown structure (WBS), identify the resource gaps, and reduce project management activities.
Answers
C.
Define the work breakdown structure (WBS), identify the resource gaps, and reduce project management activities.
D.
Formalize a scope change request with the stakeholders to adjust the project scope with the available resources.
Answers
D.
Formalize a scope change request with the stakeholders to adjust the project scope with the available resources.
Suggested answer: D