The project manager of a large construction project discovers that the blueprints received from the client appear incomplete. What should the project manager do first?

A.
Continue project execution using the current blueprints from the client.
Answers
A.
Continue project execution using the current blueprints from the client.
B.
Escalate this issue to the project sponsor.
Answers
B.
Escalate this issue to the project sponsor.
C.
Consult with the client to determine if project execution should be continued.
Answers
C.
Consult with the client to determine if project execution should be continued.
D.
Reschedule the project execution date.
Answers
D.
Reschedule the project execution date.
Suggested answer: C