Question 884 - PMP discussion

Report
Export

A labor union contract negotiation is delaying the completion of a project to build a new manufacturing plant. Because the labor contract was due for renewal this year, the project manager documented the negotiation process as a risk to the project. The project was about to start the first phase of equipment installation at the plant when the negotiation began.

How should the project manager address the situation?

A.
Acquire contract resources and submit a change request for the cost impact.
Answers
A.
Acquire contract resources and submit a change request for the cost impact.
B.
Escalate the issue to the steering committee to ask for mitigation support.
Answers
B.
Escalate the issue to the steering committee to ask for mitigation support.
C.
Log the issue and follow the planned actions in the risk response plan.
Answers
C.
Log the issue and follow the planned actions in the risk response plan.
D.
Meet with the project team to determine options for risk mitigation.
Answers
D.
Meet with the project team to determine options for risk mitigation.
Suggested answer: C