Question 893 - PMP discussion

Report
Export

A project manager working on a large-scale network implementation is frustrated with the hardware supplier. Their deliveries have been consistently late and frequently do not have vital components. The project manager's company has decided to cancel the contract and move to a new supplier, but the only other option is an overseas company.

What should the project manager do first to proceed with this change?

A.
Request assistance from the procurement department on the next steps.
Answers
A.
Request assistance from the procurement department on the next steps.
B.
Engage the services of an interpreter who understands the project domain.
Answers
B.
Engage the services of an interpreter who understands the project domain.
C.
Check social media to determine if there are any common connections that use the new supplier.
Answers
C.
Check social media to determine if there are any common connections that use the new supplier.
D.
Become aware of any cultural characteristics of the new supplier that could impact negotiation.0
Answers
D.
Become aware of any cultural characteristics of the new supplier that could impact negotiation.0
Suggested answer: A