Question 895 - PMP discussion

Report
Export

In a project progress review meeting, the end user raises concern about the quality of the construction of the project. What should the project manager do next?

A.
Request a special technical meeting.
Answers
A.
Request a special technical meeting.
B.
Refer to the requirements document.
Answers
B.
Refer to the requirements document.
C.
Review the risk management plan.
Answers
C.
Review the risk management plan.
D.
Review all implementation checklists.
Answers
D.
Review all implementation checklists.
Suggested answer: B