A team member has encountered a technical issue, similar to the one faced in a successfully closed project. However, the team member did not know about the previous project and would like to resolve the issue on their own.

What should the project manager do?

A.
Reach out to the project manager of the previous project for assistance.
Answers
A.
Reach out to the project manager of the previous project for assistance.
B.
Allow the team member to work through the issue as a training opportunity.
Answers
B.
Allow the team member to work through the issue as a training opportunity.
C.
Improve the risk management strategy and risk monitoring.
Answers
C.
Improve the risk management strategy and risk monitoring.
D.
Share the lessons learned from the previous project with the team member.
Answers
D.
Share the lessons learned from the previous project with the team member.
Suggested answer: D