Question 900 - PMP discussion

Report
Export

During the development of a new project's definition, the project manager identifies that a similar project has recently been completed. What should the project manager do first?

A.
Arrange a knowledge-sharing session.
Answers
A.
Arrange a knowledge-sharing session.
B.
Use the project management plan from the previous project.
Answers
B.
Use the project management plan from the previous project.
C.
Review the lessons learned from the previous project.
Answers
C.
Review the lessons learned from the previous project.
D.
Review the issue log from the previous project.
Answers
D.
Review the issue log from the previous project.
Suggested answer: C