Question 908 - PMP discussion

Report
Export

A project team member identified a defect in the initial solution design for a project. The stakeholders are not sure whether to deploy the system or not.

What should the project manager do?

A.
Propose a solution redesign for the project.
Answers
A.
Propose a solution redesign for the project.
B.
Revise the project's quality control measurements.
Answers
B.
Revise the project's quality control measurements.
C.
Perform risk analysis against the issue.
Answers
C.
Perform risk analysis against the issue.
D.
Develop a mitigation based on the solution design.
Answers
D.
Develop a mitigation based on the solution design.
Suggested answer: C