In a standup meeting, a team member has been providing the same update for five consecutive days. The task, which is on the critical path, is now at risk for delaying the schedule.

What should the project manager do?

A.
Keep the project sponsor informed about the delay.
Answers
A.
Keep the project sponsor informed about the delay.
B.
Reassign the task to another member of the team.
Answers
B.
Reassign the task to another member of the team.
C.
Support the team member by providing one more resource to complete the task immediately.
Answers
C.
Support the team member by providing one more resource to complete the task immediately.
D.
Ask the team member if there is an impediment, and help to remove the blockers.
Answers
D.
Ask the team member if there is an impediment, and help to remove the blockers.
Suggested answer: D