ExamGecko
Home Home / PMI / PMP
Question list
Search
Search

List of questions

Search

Related questions











Question 919 - PMP discussion

Report
Export

A team has been working for two months and has consistently missed planned user stories. How should the project manager address this issue?

A.
Ensure the sprint size is appropriate for the iteration duration.
Answers
A.
Ensure the sprint size is appropriate for the iteration duration.
B.
Engage is recruiting a highly skilled resource to reinforce the skills.
Answers
B.
Engage is recruiting a highly skilled resource to reinforce the skills.
C.
Promote changing the iteration duration in order to commit as planned.
Answers
C.
Promote changing the iteration duration in order to commit as planned.
D.
Consider using a reward system to encourage timely delivery.
Answers
D.
Consider using a reward system to encourage timely delivery.
Suggested answer: A
asked 23/09/2024
Liusel Herrera Garcia
43 questions
User
Your answer:
0 comments
Sorted by

Leave a comment first