A team has been working for two months and has consistently missed planned user stories. How should the project manager address this issue?
A.
Ensure the sprint size is appropriate for the iteration duration.
B.
Engage is recruiting a highly skilled resource to reinforce the skills.
C.
Promote changing the iteration duration in order to commit as planned.
D.
Consider using a reward system to encourage timely delivery.