Question 925 - PMP discussion
A project manager works in a startup company and is in charge of a key project that has critical and time-sensitive delivery objectives. One of the project team members missed completing an assigned deliverable on time, despite repeated assurances from the team member that it would be completed on time.
What should the project manager do next?
A.
Meet with the team member and work on a development plan for them to avoid missed deliverables in the future.
B.
Hold a team meeting to discuss team member commitments and communications.
C.
Record the issue, then refocus the team's efforts on delivering the next set of deliverables.
D.
Give the team member a formal warning for the negative impact due to failure to deliver and not meet deadlines.