Most of the work packages for a project are subcontracted. In the middle of execution, the project manager is informed that a new contract manager will take the position in one-week.

What should the project manager do next?

A.
Analyze and document the interests of the new contract manager and select a strategy to manage the relationship.
Answers
A.
Analyze and document the interests of the new contract manager and select a strategy to manage the relationship.
B.
Update the communications management plan with the new contract manager's information.
Answers
B.
Update the communications management plan with the new contract manager's information.
C.
Reschedule the next progress meeting to introduce the new contract manager to the project team.
Answers
C.
Reschedule the next progress meeting to introduce the new contract manager to the project team.
D.
Consult the project management plan and prepare a full set of documents for the new contract manager.
Answers
D.
Consult the project management plan and prepare a full set of documents for the new contract manager.
Suggested answer: A