ExamGecko
Home Home / PMI / PMP
Question list
Search
Search

List of questions

Search

Related questions











Question 932 - PMP discussion

Report
Export

One of the modules delivered by the project failed during user acceptance testing (UAT). The project manager realizes that the component that failed the functional tests was created by another team and a different functionality was approved by the business manager.

What should the project manager do?

A.
Review the integrated change control process with all the stakeholders.
Answers
A.
Review the integrated change control process with all the stakeholders.
B.
Escalate the misalignment to the project management office (PMO) and the functional manager's director.
Answers
B.
Escalate the misalignment to the project management office (PMO) and the functional manager's director.
C.
Ask the project management office (PMO) to recover the cost of fixing it from the other team's budget.
Answers
C.
Ask the project management office (PMO) to recover the cost of fixing it from the other team's budget.
D.
Request dedicated business resources to support functional testing.
Answers
D.
Request dedicated business resources to support functional testing.
Suggested answer: A
asked 23/09/2024
Shaharyar Chaudhry
42 questions
User
Your answer:
0 comments
Sorted by

Leave a comment first