Question 932 - PMP discussion
One of the modules delivered by the project failed during user acceptance testing (UAT). The project manager realizes that the component that failed the functional tests was created by another team and a different functionality was approved by the business manager.
What should the project manager do?
A.
Review the integrated change control process with all the stakeholders.
B.
Escalate the misalignment to the project management office (PMO) and the functional manager's director.
C.
Ask the project management office (PMO) to recover the cost of fixing it from the other team's budget.
D.
Request dedicated business resources to support functional testing.