A pharmacy needs to launch a medication delivery service. An interdisciplinary team was created in order to have the service ready in one-month when it usually takes five months to complete.

What should the project manager do?

A.
Register a risk and define a contingency plan.
Answers
A.
Register a risk and define a contingency plan.
B.
Review and reduce the project backlog.
Answers
B.
Review and reduce the project backlog.
C.
Assist the team in proposing a minimum viable product (MVP).
Answers
C.
Assist the team in proposing a minimum viable product (MVP).
D.
Ask to increase the capacity of the team.
Answers
D.
Ask to increase the capacity of the team.
Suggested answer: C