Question 948 - PMP discussion

Report
Export

A project manager had to schedule additional planning sessions to add requirements from an international stakeholder. The stakeholder expressed concern about the product not meeting the client's needs.

Which factor should the project manager have considered when developing the product?

A.
Responsibility matrix
Answers
A.
Responsibility matrix
B.
Stakeholder's location
Answers
B.
Stakeholder's location
C.
Availability of resources
Answers
C.
Availability of resources
D.
Stakeholder's needs
Answers
D.
Stakeholder's needs
Suggested answer: D