A project manager has been newly assigned to an existing project. The project manager noted that the input from a business unit, which is critical to the success of the project, was not included in any project assets. Instead, there were many complaints about the project's operational results and the alignment with solutions affected by the business unit's operations.

What action should the project manager take?

A.
Validate that the project requirements information is up-to-date.
Answers
A.
Validate that the project requirements information is up-to-date.
B.
Determine the degree to which the project is in compliance.
Answers
B.
Determine the degree to which the project is in compliance.
C.
Optimize alignment among needs, expectations, and project objectives.
Answers
C.
Optimize alignment among needs, expectations, and project objectives.
D.
Determine a strategy for change responses to new objective requests.
Answers
D.
Determine a strategy for change responses to new objective requests.
Suggested answer: C