List of questions
Related questions
Question 960 - PMP discussion
A project is on its second iteration out of eight. After some daily meetings, the project manager notices that one team member is always directing the meeting. The team is not comfortable with the situation and, as a result, the activities are blocked.
What should the project manager do?
A.
Conduct a session to help the team improve their interactions.
B.
Update the risk register and define a contingency plan.
C.
Moderate the daily meetings to help the team to feel more comfortable.
D.
Meet with the team member to show the impact of their behavior.
Your answer:
0 comments
Sorted by
Leave a comment first