A steering committee has asked the project manager to assist with the decision-making process between build versus buy delivery options. Which value metric should the project manager evaluate to respond to the steering committee's request?

A.
Net present value (NPV)
Answers
A.
Net present value (NPV)
B.
Earned value (EV)
Answers
B.
Earned value (EV)
C.
Impact value
Answers
C.
Impact value
D.
Expected monetary value (EMV)
Answers
D.
Expected monetary value (EMV)
Suggested answer: A
asked 23/09/2024