List of questions
Related questions
Question 971 - PMP discussion
A project manager is managing a new type of project for a traditional organization. The culture of the organization is not typically in support of change.
Which two factors should the project manager consider in developing the portion of the project plan related to culture? (Choose two.)
A.
The relevant experience and qualifications of each team member.
B.
The amount of flexibility the team exercises while doing work.
C.
The amount of risk the organization is willing to accept.
D.
The speed the team can perform without compromising quality.
E.
The influence of the stakeholders on the project.0
Your answer:
0 comments
Sorted by
Leave a comment first