A project lead is managing a construction project in an isolated location. There have been delays due to difficult working conditions, which include team sickness and absences.

How should the project lead manage those issues to get the project back on track?

A.
Ask for additional budget because the project end will be delayed.
Answers
A.
Ask for additional budget because the project end will be delayed.
B.
Identify the causes of the issues in order to find a suitable solution.
Answers
B.
Identify the causes of the issues in order to find a suitable solution.
C.
Review the project scope in order to simplify it and shorten project duration.
Answers
C.
Review the project scope in order to simplify it and shorten project duration.
D.
Ask human resources (HR) to find individuals to replace team members.
Answers
D.
Ask human resources (HR) to find individuals to replace team members.
Suggested answer: B