A project manager is working in a constantly changing business environment. In order to address this situation, the project manager has decided to use a collaborative leadership style.
Which landscape describes the project environment?
A.
High accountability, little authority
B.
Good roadmaps, little accountability
C.
Available resources, bad roadmaps
D.
Enough authority, insufficient resources