A project is nearing the completion of a sprint when the product owner announces that a local regulator has banned part of the deliverable. What should the project manager do?

A.
Complete the sprint and seek a waiver from the regulator.
Answers
A.
Complete the sprint and seek a waiver from the regulator.
B.
Perform a sprint risk assessment and analyze challenges.
Answers
B.
Perform a sprint risk assessment and analyze challenges.
C.
Add more items to the sprint backlog that will add value.
Answers
C.
Add more items to the sprint backlog that will add value.
D.
Complete the sprint, but do not release the deliverable.
Answers
D.
Complete the sprint, but do not release the deliverable.
Suggested answer: B