Question 997 - PMP discussion
A project team is finishing a sprint to deliver a key deliverable. The project team tells the project manager that the deliverable does not meet the agreed project standards set out by the customer and insists on reworking the deliverable to meet the standards. This will delay the project by two weeks.
What should the project manager do?
A.
Agree with the team that the best way forward is to improve the quality of the deliverable to meet the standards even if it takes more time.
B.
Let the team rework the deliverable and delay the delivery of the project by two weeks.
C.
Ask the team to move forward with the deliverable with the best possible quality without extending the time.
D.
Meet with the sponsor to highlight the poor quality standards and ask for two weeks of additional time to rework the deliverable.
Your answer: