A customer approaches the product owner with a new requirement and asks for a rough estimation to implement it. The outline of the task would be similar to a prior deliverable.
What should the product owner do to properly inform the customer?
A.
Analyze the current backlog and the backlog refinement to determine a gap for fulfilling the requirement.
B.
Check the work breakdown structure (WBS) and the cost estimation for the similar requirement and provide an estimate for the new requirement.
C.
Revisit the user story of the similar requirement, learn about its story points and velocity, and sketch out the time needed for this requirement.
D.
Refer to the lessons learned register where the experience and effort of former requirements should have been noted.