Question 1018 - PMP discussion
A team lead for a project that is currently in execution with multiple delivery teams is issuing status updates. This communication was not discussed with the project manager, and the project stakeholders are concerned about nonalignment since other teams are not providing these updates.
What should the project manager do?
A.
Instruct the team lead to stop sending the update report.
B.
Discuss with the team lead to understand the reason for the report.
C.
Examine the project reporting requirements with the stakeholders.
D.
Tell the other team leads to provide similar update reports.