Question 1024 - PMP discussion
A project manager is working on a project for a startup company. The company launched cloudbased agile project management and DevOps training modules via the learning platform to support multiple self-paced and virtual learning formats. In a recent sprint, the quality assurance team failed to thoroughly inspect the modules before deployment, resulting in a poor customer experience.
Which of the following issues is the project manager facing?
A.
Nonconformance issue
B.
Escaped defect
C.
Unmet planned-to-done ratio
D.
Undetected error