A bank has initiated a project to replace an existing core system with a new one. The system will be launched in several stages after the completion of each project deliverable that must be approved by the key stakeholders.
What should the project manager do first?
A.
Engage experienced key stakeholders in the implementation of the project.
B.
Review the test and inspection plan with the key stakeholders.
C.
Agree on quality standards with the key stakeholders.
D.
Develop a requirements traceability matrix.