Question 1033 - PMP discussion
An agile senior project team member suddenly resigns from the organization. Following this departure, the remaining team members are having difficulty accessing information and are unable to complete a deliverable.
What should the project manager have done to avoid this situation?
A.
Ensured the project repository is up to date.
B.
Made an effort to reemploy the senior project team member.
C.
Updated the job descriptions for all team roles.
D.
Provided specialist training for all team members.
Your answer: